Service Mapping Implementation Time vs Complexity

What is the Time To Value for Service Mapping projects?

Scope

HighMediumSimple

Key Takeaways

  • Most service mapping projects required between 5–12+ months for implementation, particularly as the number of mapped applications increased.
  • Medium- and high-complexity projects were associated with the longest implementation timelines, with several projects mapping over 400–500 applications.
  • Simpler projects were generally completed faster and involved fewer mapped applications, although some large-scale simple environments still extended beyond 12 months.
  • Overall, the findings suggest a strong relationship between project scope, application volume, and implementation duration in service mapping initiatives.